Skip to main content

Contributing Factors

Human Error

Damage and Injuries

Any

Equipment

Any

Probable Cause

Any

Contributing Factors

Human Error
Show more

Damage and Injuries

Any

Equipment

Any
Show more

Probable Cause

Any
Show more

CHECK OUT OUR MOST RELEVANT INCIDENT LISTINGS!

Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.

Do not interconnect hydrogen drain trap lines with other drain lines

Thoroughly inspect equipment installation to manufacturer’s installation instructions

Warn against unauthorized field modifications

Consult the…

1. Increase physical protection, shielding, and securing of transported hydrogen tube valves, piping, and fittings from multi-directional forces that are likely to occur during accidents, including rollovers. Reference: 49 Code of Federal…

1. All samples with potential for hydrogen buildup should be limited to ground shipment only. (This shipment was by ground and air. If this incident were to have happened in an airplane, the consequences may have been worse.)

2. All samples…

  1. A hydrogen tube pressure indication system needs to be developed that is robust enough to withstand an accident, indicates hydrogen pressure regardless of valve position, and would be visible from a safe distance during an accident situation…

Hazard analysis should consider potential leak locations, potential ignition sources in the vicinity, and the potential for accumulating flammable gases in that area.

Users should leak-check all cylinders upon installation. This event…

No Lessons Learned, Specific Suggestions for Avoidance, or Mitigation Steps Taken.

Procedures will be revised to include specific information about hydrogen sensors and alarm controls. Caution will be added about sparks and flames in the fuel cell operation area. Workers will be cautioned that shunt resistors may reach high…

Management should ensure that a complete and thorough review of the previous work activities identified in the work package is performed at the pre-job briefing for the planned work. Work activities should be discontinued if any confusion exists…

This occurrence highlights the need for ensuring work is organized and planned in a manner that is practical and efficient. The primary lesson learned from this occurrence is that personnel must be cognizant of the impact of their actions on…

  1. Parallel-path design activities require an increased level of management oversight and control to mitigate the risks inherent in this process.
  2. Schedule pressure cannot be allowed to compromise the integrity of the design process…

In this case, failure to recognize a run of tubing still maintaining pressure could have been avoided if such information was provided in a safety briefing. Knowledge of any job is the utmost importance in promoting and maintaining a safe working…

This incident highlights the need to ensure that the performance of special procedures does not place facility equipment in a condition that could lead to entry into a LCO.

  1. Maintenance work scopes must be adhered to. If added work is approved, it must be tracked and reviewed to ensure that the equipment is inspected by operations personnel. Scheduled work and extra work should be listed and checked off for…
  1. Train personnel on delivery procedures and emphasize the safety aspects of hydrogen connections and disconnections, and verification of clearance for trailer movement prior to departure.
  2. Provide site-specific delivery procedures…

Installation

  1. Fittings need to be visually inspected to insure ferules are in place and correctly positioned prior to swageing.
  2. Research staff are responsible for communicating system specifications [gas type,…

The practice of making gas mixtures in the laboratory should be eliminated, and gas mixtures with a known low hydrogen concentration should be purchased for use. The concentration of hydrogen used should be such that it is not possible to form an…

After this accident, a safety inspection team was organized. An investigation of this incident and an inspection of all other experimental equipment was conducted by the team. As a result of this inspection, the heaters are now hard-wired to the…

When performing maintenance evolutions, proper work control processes must be in place to insure that process systems are adequately prepared, remain in a safe energy state during the maintenance evolution, and are properly restored afterwards.…

The primary lesson learned was that the active hydrogen facility and existing operating procedure, at the time of the accident, were sound. While this now has been determined, the previous form(s) of this system, associated documentation, and…

Although most of the hydrogen fluoride piping system was open to the atmosphere before the elbow was cut, the lines were not purged. Two plugs of residual material on either side of the elbow remained in place, thus allowing hydrogen to be…

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / CauseEquipment Design or SelectionComponent FailureOperational ErrorInstallation or MaintenanceInadequate Gas or Flame DetectionEmergency Shutdown ResponseOther or Unknown
Hydrogen Gas Metal Cylinder or Regulator 3/31/2012
4/30/1995
2/6/2013
4/26/201012/31/1969  3/17/1999
11/1/2001
12/23/2003
Piping/Valves4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/20091/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009
9/1/1992
10/31/1980
10/3/2008 
Tubing/Fittings/Hose 9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/19829/30/2004
10/7/2005
 10/7/2005 
Compressor 10/5/2009
6/10/2007
8/21/2008
1/15/2019
  10/5/20098/21/2008 
Liquid Hydrogen Tank or Delivery Truck4/27/198912/19/2004
1/19/2009
8/6/200412/31/1969 1/1/197412/17/2004
Pressure Relief Device7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969    
Instrument1/15/20193/17/1999
12/31/1969
2/6/2013
  11/13/73  
Hydrogen Generation Equipment7/27/1999  10/23/2001   
Vehicle or Lift Truck 7/21/2011    2/8/2011
12/9/2010
Fuel Dispenser 8/2/2004
5/1/2007
6/11/2007
9/19/2007
 2/24/2006
1/22/2009
   
Fuel Cell Stack      5/3/2004
12/9/2010
2/8/2011
Hydrogen Cooled Generator   12/31/1969
2/7/2009
   
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
 11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
  6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire
We are professional and reliable provider since we offer customers the most powerful and beautiful themes. Besides, we always catch the latest technology and adapt to follow world’s new trends to deliver the best themes to the market.

Contact info

We are the leaders in the building industries and factories. We're word wide. We never give up on the challenges.

Recent Posts