Skip to main content

Hydrogen Alarm Activates in Processing Facility

Severity
Incident
Was Hydrogen Released?
Yes
Was There Ignition?
No
Incident Date
Incident Attributes
Damage and Injuries
Probable Cause
When Incident Was Discovered
Describe the incident, including corrective steps taken and their result.

A process area alarm activated. The alarm was caused by an instrument channel located above a reaction vessel off-gas system final HEPA filter canister, which indicated 25% of the lower explosive limit (LEL) for hydrogen. Since the only source of hydrogen is from the reaction vessel during the reaction of sodium with concentrated sodium hydroxide, the immediate actions were to shutdown the reaction process and place the facility in a safe condition.

The root cause was inadequate or defective design. Had the pre-filter drains been vented to outside the building, no hydrogen could accumulate in the process area. The corrective action for this is to complete an Engineering Task Authorization (ETA) to install a sample/drain collection system with loop seals to prevent any release of hydrogen to the process area. The direct cause was the pre-filter canister drain valve being left open after the fluid stopped draining, which allowed hydrogen from the reaction vessel off-gas system to accumulate, causing the alarm at 1% hydrogen in air. A contributing cause may have been that the operator was not properly instructed to shut the valve immediately when the fluid stopped draining. Corrective action for this is to issue improved instructions for sampling/draining the off gas system and training the operators on these improved procedures. An ETA was also initiated to provide interlocks and administrative controls to ensure the process area roof exhaust fans are running prior to beginning reaction vessel sodium injection and stop sodium injection should either fan stop running.

The source of the hydrogen released to the process area was traced to the routine operation of draining accumulated fluid from the one of two off-gas system pre- filter canisters. This is done to the off line filter canister every six hours when the filters are shifted. This has been done routinely since the filter drains were installed. Approximately 188 hours of sodium reaction at .75 gpm sodium flow has been completed with no other hydrogen alarms being received. The sodium reaction process was restarted a few hours later with concurrence of facility management. Hydrogen leak checks were completed on the off-gas system with none found.

Lessons Learned

Hazard assessment is critical during the design, fabrication, and installation of system modifications to ensure hazards and potential hazards are addressed prior to system start-up and operation.

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / CauseEquipment Design or SelectionComponent FailureOperational ErrorInstallation or MaintenanceInadequate Gas or Flame DetectionEmergency Shutdown ResponseOther or Unknown
Hydrogen Gas Metal Cylinder or Regulator 3/31/2012
4/30/1995
2/6/2013
4/26/201012/31/1969  3/17/1999
11/1/2001
12/23/2003
Piping/Valves4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/20091/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009
9/1/1992
10/31/1980
10/3/2008 
Tubing/Fittings/Hose 9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/19829/30/2004
10/7/2005
 10/7/2005 
Compressor 10/5/2009
6/10/2007
8/21/2008
1/15/2019
  10/5/20098/21/2008 
Liquid Hydrogen Tank or Delivery Truck4/27/198912/19/2004
1/19/2009
8/6/200412/31/1969 1/1/197412/17/2004
Pressure Relief Device7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969    
Instrument1/15/20193/17/1999
12/31/1969
2/6/2013
  11/13/73  
Hydrogen Generation Equipment7/27/1999  10/23/2001   
Vehicle or Lift Truck 7/21/2011    2/8/2011
12/9/2010
Fuel Dispenser 8/2/2004
5/1/2007
6/11/2007
9/19/2007
 2/24/2006
1/22/2009
   
Fuel Cell Stack      5/3/2004
12/9/2010
2/8/2011
Hydrogen Cooled Generator   12/31/1969
2/7/2009
   
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
 11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
  6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire
We are professional and reliable provider since we offer customers the most powerful and beautiful themes. Besides, we always catch the latest technology and adapt to follow world’s new trends to deliver the best themes to the market.

Contact info

We are the leaders in the building industries and factories. We're word wide. We never give up on the challenges.

Recent Posts