Skip to main content

Hydrogen Cylinder Leak at Fueling Station

Severity
Incident
Was Hydrogen Released?
Yes
Was There Ignition?
No
Incident Date
Incident Attributes
Setting
Equipment
Damage and Injuries
Probable Cause
Characteristics
When Incident Was Discovered
Describe the incident, including corrective steps taken and their result.

An alarm sounded at a recently inaugurated hydrogen fueling station in a major metropolitan area. One out of a total of 120 high-pressure hydrogen cylinders, located on the roof of the fueling station, failed in service. Gaseous hydrogen was leaking from a screw fitting of the cylinder, but the hydrogen was not ignited. Three hydrogen gas sensors detected the leakage and triggered an alarm that resulted in an immediate emergency shutdown, isolating the leaking high-pressure cylinder bank from the other three banks and notifying the local fire department. No personnel were allowed to enter the roof area, approximately 7-9 meters above ground level.

The police isolated the area around the fueling station within a radius of 200 meters. The maximum content of the leaking cylinder bank was determined to be ~ 70 kg of hydrogen at 800 bar. The leak rate at the high-pressure storage bank was ~5 kg/hr.

After 2.5 hours, the hydrogen supplier's technician manually opened a bypass line to let the hydrogen escape through a vent line. This action was taken from the ground-floor control room well outside an area that might have exposed personnel to additional hazards.

About four hours later, the leaking high-pressure bank was essentially empty, with a pressure of around 1 bar. The cylinder with the failed teflon-sealed screw fitting was sealed with a plug with the intention of never using it again. There was no threat to employees or the public from this incident.

Lessons Learned
  1. The hydrogen supplier installed a fire-resistant material board adjacent to the high-pressure hydrogen storage banks to prevent any potential jet flames from affecting adjacent high-pressure cylinders for several minutes. The 0.25 mm sandwich board of fiberglass-reinforced, lightweight concrete is easy to maintain and does not rot under outside conditions. This safety measure was implemented just three days after the incident occurred, although it had been planned for a long time.
  2. The hydrogen supplier installed a semi-automated sprinkler system to cool the high-pressure hydrogen storage banks to prevent any potential escaping hydrogen gas that might ignite in jet flames from affecting other hydrogen cylinders. In addition, the dry piping system above the high-pressure hydrogen storage banks can be flooded with water by the fire department in case of fire or leakages in the high-pressure banks.
  3. The alarm system was refined to send automated messages to relevant personnel informing them of gas/fire alarms.
  4. The remote control room where service personnel are monitoring the fueling station is now equipped with an additional audio system to draw faster attention to alarms.
  5. All plans and emergency procedures have been reviewed, adjusted and edited to document changes and fully capture the lessons learned.
  6. Other learnings: Training for worst-case scenarios is recommended in order to be prepared for those siutations.

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / CauseEquipment Design or SelectionComponent FailureOperational ErrorInstallation or MaintenanceInadequate Gas or Flame DetectionEmergency Shutdown ResponseOther or Unknown
Hydrogen Gas Metal Cylinder or Regulator 3/31/2012
4/30/1995
2/6/2013
4/26/201012/31/1969  3/17/1999
11/1/2001
12/23/2003
Piping/Valves4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/20091/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009
9/1/1992
10/31/1980
10/3/2008 
Tubing/Fittings/Hose 9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/19829/30/2004
10/7/2005
 10/7/2005 
Compressor 10/5/2009
6/10/2007
8/21/2008
1/15/2019
  10/5/20098/21/2008 
Liquid Hydrogen Tank or Delivery Truck4/27/198912/19/2004
1/19/2009
8/6/200412/31/1969 1/1/197412/17/2004
Pressure Relief Device7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969    
Instrument1/15/20193/17/1999
12/31/1969
2/6/2013
  11/13/73  
Hydrogen Generation Equipment7/27/1999  10/23/2001   
Vehicle or Lift Truck 7/21/2011    2/8/2011
12/9/2010
Fuel Dispenser 8/2/2004
5/1/2007
6/11/2007
9/19/2007
 2/24/2006
1/22/2009
   
Fuel Cell Stack      5/3/2004
12/9/2010
2/8/2011
Hydrogen Cooled Generator   12/31/1969
2/7/2009
   
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
 11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
  6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire
We are professional and reliable provider since we offer customers the most powerful and beautiful themes. Besides, we always catch the latest technology and adapt to follow world’s new trends to deliver the best themes to the market.

Contact info

We are the leaders in the building industries and factories. We're word wide. We never give up on the challenges.

Recent Posts