Severity
Near-Miss
Leak
Yes
Ignition
No

A power plant reported a hydrogen leak inside an auxiliary building. The given plant was in cold shutdown at the time of the event. The discovery of this problem was as a result of an unassociated event involving the activation of a chlorine monitor in the control building. When additional samples indicated no chlorine gas, the shift supervisor ordered further investigation into other plant areas. Because there was no installed detection equipment, portable survey instruments were used to determine gaseous mixtures. Hydrogen was detected in the auxiliary building at 20 to 30 percent of the lower flammability limit (LFL) for hydrogen. A level of about 30 percent of LFL corresponds to about 1.2 percent hydrogen by volume.

When hydrogen was discovered in the auxiliary building, the operator isolated the cryogenic hydrogen skid outside the turbine building and soon located the source of the leak as packing on a globe valve in a small line to the volume control tank (VCT). The operator opened doors that quickly caused the hydrogen to dissipate. The globe valve was of a conventional design and had no special packing. The globe valve was located in a vertical pipe chase where little ventilation was present because of ongoing HVAC testing. Besides being used as a cover gas in the VCT, hydrogen from the skid is used to cool the generator.

Incident Date
Apr 20, 1987
Setting
Equipment
  • Piping/Fittings/Valves
  • Piping
  • Piping/Fittings/Valves
  • Valve
  • Ventilation System
  • Exhaust Fan
Damage and Injuries
Probable Cause
Contributing Factors
When Incident Discovered
Lessons Learned

The lessons of this event fall into five categories: (1) proper in-plant communications during events, (2) proper valve application for use with hydrogen, (3) excess flow check valve set point, (4) heating and ventilation and air conditioning (HVAC) maintenance and flow testing, and (5) hydrogen line routing. The operator is examining ways to improve communications in the plant during events and the training of personnel in reading portable instruments.

As another corrective measure, the operator is examining the use of other types of valves, such as valves with a diaphragm or bellows rather than conventional stem packing, in lines containing hydrogen. The operator is also examining the set point for the excess flow check valves on the hydrogen lines. These check valves are designed to limit the flow of hydrogen in the event of a large leak so that when combined with proper ventilation in rooms with hydrogen lines, hydrogen levels would remain within specified limits throughout the plant.

This plant had HVAC flow balancing problems during the preparation for plant startup. Generally HVAC flow balance is based on the heat loads and the resultant room temperatures under normal and accident conditions. However, this event demonstrates that hydrogen concentrations also may need to be considered to set a lower limit on the ventilation in rooms that contain hydrogen lines.

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / Cause Equipment Design or Selection Component Failure Operational Error Installation or Maintenance Inadequate Gas or Flame Detection Emergency Shutdown Response Other or Unknown
Hydrogen Gas Metal Cylinder or Regulator   3/31/2012
4/30/1995
2/6/2013
4/26/2010 12/31/1969     3/17/1999
11/1/2001
12/23/2003
Piping/Valves 4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/2009 1/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009

9/1/1992
10/31/1980

10/3/2008  
Tubing/Fittings/Hose   9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/1982 9/30/2004
10/7/2005
  10/7/2005  
Compressor   10/5/2009
6/10/2007
8/21/2008
1/15/2019
    10/5/2009 8/21/2008  
Liquid Hydrogen Tank or Delivery Truck 4/27/1989 12/19/2004
1/19/2009
8/6/2004 12/31/1969   1/1/1974 12/17/2004
Pressure Relief Device 7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969        
Instrument 1/15/2019 3/17/1999
12/31/1969
2/6/2013
    11/13/73    
Hydrogen Generation Equipment 7/27/1999     10/23/2001      
Vehicle or Lift Truck   7/21/2011         2/8/2011
12/9/2010
Fuel Dispenser   8/2/2004
5/1/2007
6/11/2007
9/19/2007
  2/24/2006
1/22/2009
     
Fuel Cell Stack            

5/3/2004
12/9/2010
2/8/2011

Hydrogen Cooled Generator       12/31/1969
2/7/2009
     
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
  11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
    6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire