Skip to main content

Flash Fire Occurs on Construction Project

Severity
Incident
Was Hydrogen Released?
Yes
Was There Ignition?
Yes
Ignition Source
Band saw
Incident Attributes
Describe the incident, including corrective steps taken and their result.

A subcontractor employee was using a band saw to cut a 1" metal pipe when a flash fire occurred on the third floor hydrogen fluoride area. Subcontractor employees were removing all piping associated with the Anhydrous Hydrofluoric Acid (AHF) system. These lines were being removed during plant decontamination and demolition (D&D). The subcontractor employee was attempting to cut a 90-degree elbow located at the highest elevation on the 1" line, but the lowest elevation of the overall piping run. Since hydrogen is lighter than air, it is speculated that a minute amount of hydrogen gas had accumulated in the elbow.

Even though Safe Shutdown personnel had previously opened the system and placed it in a safe configuration, residual hydrogen fluoride could have still reacted with the metal piping to create hydrogen gas. The subcontractor employee began to cut the elbow with a portable electric band saw. Once the heat generated by the band saw came into contact with the hydrogen gas, an extremely rapid exothermic chemical reaction with a resulting flash fire occurred. There was no significant impact to on-site or off-site personnel as a result of this occurrence.

The subcontractor employee performing the cutting immediately walked to the temporary safety shower, located less than 15 feet away, and thoroughly rinsed his chemical resistant personal protective equipment (PPE). A second employee readied a fire extinguisher, also less than 15 feet away, but it was never discharged due to the short duration of the event. The first employee left the temporary shower, doffed the outer set of anti-c's, and proceeded to the decontamination area. Upon arrival at the decontamination area, the employee doffed his inner set of anti-c's and showered a second time for twenty minutes as a safety precaution.

The employee exhibited no physical injuries, but was sent to medical for verification. The employee had been wearing cotton anti-contamination clothing and a second set of chemical resistant anti-c's. The flash fire caused the chemical-resistant clothing to melt, similar to a marshmallow, on the right side of the employee's body. The cotton anti-c's located underneath the chemical resistant anti-c's revealed no physical signs of heat damage as a result of the flash fire, most likely due to the employee's quick activation of the safety shower and/or short duration of the event.

The root cause of the event was determined to be a defective or inadequate procedure. The facility did not identify hydrogen off-gas as a potential hazard in the hydrogen fluoride process lines of the plant. If this issue had been properly addressed, it is less likely that this event would have occurred.

Lessons Learned

Although most of the hydrogen fluoride piping system was open to the atmosphere before the elbow was cut, the lines were not purged. Two plugs of residual material on either side of the elbow remained in place, thus allowing hydrogen to be trapped in the elbow. In the future, piping systems containing hydrogen fluoride or other chemicals should be purged to ensure that they are free from hazards prior to starting D&D activities.

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / CauseEquipment Design or SelectionComponent FailureOperational ErrorInstallation or MaintenanceInadequate Gas or Flame DetectionEmergency Shutdown ResponseOther or Unknown
Hydrogen Gas Metal Cylinder or Regulator 3/31/2012
4/30/1995
2/6/2013
4/26/201012/31/1969  3/17/1999
11/1/2001
12/23/2003
Piping/Valves4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/20091/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009
9/1/1992
10/31/1980
10/3/2008 
Tubing/Fittings/Hose 9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/19829/30/2004
10/7/2005
 10/7/2005 
Compressor 10/5/2009
6/10/2007
8/21/2008
1/15/2019
  10/5/20098/21/2008 
Liquid Hydrogen Tank or Delivery Truck4/27/198912/19/2004
1/19/2009
8/6/200412/31/1969 1/1/197412/17/2004
Pressure Relief Device7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969    
Instrument1/15/20193/17/1999
12/31/1969
2/6/2013
  11/13/73  
Hydrogen Generation Equipment7/27/1999  10/23/2001   
Vehicle or Lift Truck 7/21/2011    2/8/2011
12/9/2010
Fuel Dispenser 8/2/2004
5/1/2007
6/11/2007
9/19/2007
 2/24/2006
1/22/2009
   
Fuel Cell Stack      5/3/2004
12/9/2010
2/8/2011
Hydrogen Cooled Generator   12/31/1969
2/7/2009
   
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
 11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
  6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire
We are professional and reliable provider since we offer customers the most powerful and beautiful themes. Besides, we always catch the latest technology and adapt to follow world’s new trends to deliver the best themes to the market.

Contact info

We are the leaders in the building industries and factories. We're word wide. We never give up on the challenges.

Recent Posts