Severity
Incident
Leak
Yes
Ignition
Yes

An explosion occurred within the hydrogen processing system of a chemical plant that produces sodium chlorate for bleaching pulp and paper. The chemical process utilizes electrolytic cells and is pH-dependent. Hydrogen is produced as a byproduct and is utilized as a fuel.

At the time of the incident, the plant was at an abnormal operating level of 25% capacity. A non-routine maintenance operation to repair high-pH liquid piping was in progress. To assist, operations personnel rerouted the high-pH liquid stream to the plant sump. However, in doing this, the liquid eventually made its way back into the electrolytic process by design. Ultimately this created the root cause of the explosive condition in that the pH of the electrolytic process increased faster than the computer-controlled acid-injection system could compensate for in this abnormal setup. (The acid system is designed to maintain proper process pH by lowering pH in the electrolytic process.) As the amount of high-pH electrolyte circulating through the system continued to increase, so did the amount of oxygen generated by the electrolytic process until the hydrogen concentration fell below the upper flammability limit (UFL). In spite of existing standard operating procedures (SOPs) and training, operations personnel on duty failed to realize and act according to the seriousness of the condition, and also questioned instrument readings.

After operating with the increased oxygen level and the hydrogen concentration below the UFL for several hours, the hydrogen ignited and an explosion occurred in the system. The explosion caused extensive damage to piping, process vessels and the containment building, but did not start a fire or cause any injuries. This event shut down the manufacturing process for over a week for emergency repairs.

Incident Date
Dec 28, 2007
Setting
Equipment
  • Piping/Fittings/Valves
  • Piping
  • Process Equipment
  • Process Vessels
Damage and Injuries
When Incident Discovered
Lessons Learned

Provide additional retraining of operators. Curriculum should emphasize the proper response to high oxygen in the hydrogen gas.
Evaluate current knowledge of operators. Operators should know proper response, such as contacting engineering or management support as needed, to evaluate any potentially dangerous process conditions they might observe.
Revise interlock strategy. The plant control system was reviewed and enhanced with additional interlocks that automatically shut down the process and safely secure the hydrogen systems on certain pH levels and certain oxygen levels.

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / Cause Equipment Design or Selection Component Failure Operational Error Installation or Maintenance Inadequate Gas or Flame Detection Emergency Shutdown Response Other or Unknown
Hydrogen Gas Metal Cylinder or Regulator   3/31/2012
4/30/1995
2/6/2013
4/26/2010 12/31/1969     3/17/1999
11/1/2001
12/23/2003
Piping/Valves 4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/2009 1/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009

9/1/1992
10/31/1980

10/3/2008  
Tubing/Fittings/Hose   9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/1982 9/30/2004
10/7/2005
  10/7/2005  
Compressor   10/5/2009
6/10/2007
8/21/2008
1/15/2019
    10/5/2009 8/21/2008  
Liquid Hydrogen Tank or Delivery Truck 4/27/1989 12/19/2004
1/19/2009
8/6/2004 12/31/1969   1/1/1974 12/17/2004
Pressure Relief Device 7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969        
Instrument 1/15/2019 3/17/1999
12/31/1969
2/6/2013
    11/13/73    
Hydrogen Generation Equipment 7/27/1999     10/23/2001      
Vehicle or Lift Truck   7/21/2011         2/8/2011
12/9/2010
Fuel Dispenser   8/2/2004
5/1/2007
6/11/2007
9/19/2007
  2/24/2006
1/22/2009
     
Fuel Cell Stack            

5/3/2004
12/9/2010
2/8/2011

Hydrogen Cooled Generator       12/31/1969
2/7/2009
     
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
  11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
    6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire