Liquid Hydrogen Delivery Truck Fire

First Name
Andy
Last Name
Piatt

A fire erupted from a tanker truck delivering liquid hydrogen to a factory. The ignition of leaking vapors created a plume of flames that rose dozens of feet into the air. The flames receded within seconds, leaving the truck with little damage and its driver unharmed.

The truck was off-loading hydrogen into a tank behind the plant when the incident occurred. The plant reported no delays in its production. It uses the hydrogen in various processes.

Hydrogen Storage -Ammonia Borane (AB) Loaded onto Mesoporous Carbon

First Name
Andy
Last Name
Piatt

During preparation of a new hydrogen storage material, ammonia borane (AB) loaded onto mesoporous carbon, an unexpected incident was observed. As with all procedures with new materials the work is conducted on a small scale and in a laboratory fume hood. They followed the procedures that they had used for absorption of ammonia borane onto mesoporous silica without incident.

Small Electrical Fire Resulting from Improper Equipment Configuration

First Name
Andy
Last Name
Piatt

An employee noticed an unusual smell in a fuel cell laboratory. A shunt inside experimental equipment overheated and caused insulation on conductors to burn. Flames were approximately one inch high and very localized. The employee de-energized equipment and blew out the flames. No combustible material was in the vicinity of the experiment. The fire was contained within the fuel cell and resulted in no damage to equipment.

Sodium Hydride Spontaneously Ignites During Weighing

First Name
Andy
Last Name
Piatt

A guest student was weighing out less than 200 mg of sodium hydride. The material reacted with moisture in the air, producing hydrogen. The heat of the reaction ignited the hydrogen on the end of the spatula being used to transfer the material and at the mouth of the bag holding the stock material (approximately 48 to 50 g). The student attempted to smother the flames with a cotton lab coat hanging nearby. He quickly determined that the lab coat was insufficient to smother the flames and entered the adjoining lab to get a fire extinguisher and warn other lab workers in the area.

Swagelok Fittings Under High Pressure

First Name
Andy
Last Name
Piatt

A shop supervisor determined that a second shift would be necessary to complete some priority work on the spare hydrogen mitigation pump. The work scope for the shift would be dedicated to continued fabrication of designed tubing runs, repairs to existing tubing with known leaks and pressure testing of other various tubing runs. The shift craft complement would include three pipe fitters, one welder, one QC inspector and a shift supervisor.

Roofing Work Condition Outside Authorization Basis

First Name
Andy
Last Name
Piatt

A facility manager was notified that an authorization basis requirement, associated with roofing contractor work, had not been met. The requirement was that an unused hydrogen gas cylinder adjacent to the building and not connected to a manifold be removed prior to the use of propane tanks for the hot tar portion of the work.

The project manager failed to remove the extra gas bottle as required because he did not recognize from the bottle color and lack of stencil that the bottle contained hydrogen.

Explosion in Refrigerator

First Name
Andy
Last Name
Piatt

A 30-milliliter (mL) vacuum bulb, equipped with a glass stopcock, containing one gram of pentacarbonyl manganese hydride exploded in a refrigerator. This caused the breakage of three other containers, releasing some contents into the refrigerator. The chemicals did not react. The refrigerator contained numerous reactive and flammable chemicals, mostly in glass containers.

Non-Sparking Tools Used for Intrusive Work

First Name
Andy
Last Name
Piatt

A facility representative observed pipe-fitters enter a containment tent around a riser with a tool bag that contained a mixture of steel and copper/beryllium tools. The top flange was loosened using a copper/beryllium socket and a steel torque wrench. When questioned, the pipe-fitters correctly stated that this was allowable for initial loosening and tightening of these bolts. A copper/beryllium ratchet was used to accomplish the bolt removal. The bonded riser was shifted to allow access for the IH technician.

Reactive Chemical Treatment Causes Beaker to Shatter

First Name
Andy
Last Name
Piatt

A violent reaction occurred while hydrolyzing metal in water. The reactive metal treatment began with a review of the chemical inventory and setup of reaction vessels. The sodium metal was cut in shavings and added one at a time to the reaction vessel. After the second addition, an argon purge was added to disperse hydrogen gas faster. After approximately 10 pieces had been treated, the glass beaker shattered, releasing the contents of the reaction vessel (1 liter) inside the hood and causing the chemist's hand to receive superficial cuts.