Skip to main content

Contributing Factors

Any

Damage and Injuries

None

Equipment

Any

Probable Cause

Any

Contributing Factors

Any
Show more

Damage and Injuries

None

Equipment

Any
Show more

Probable Cause

Any
Show more

CHECK OUT OUR MOST RELEVANT INCIDENT LISTINGS!

Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.

Whenever a new program or organization is created, management should ensure that program interfaces and new responsibilities are clearly defined. Effective program integration is necessary to ensure that all responsibilities and requirements are…

Procedures will be revised to include specific information about hydrogen sensors and alarm controls. Caution will be added about sparks and flames in the fuel cell operation area. Workers will be cautioned that shunt resistors may reach high…

Management should ensure that a complete and thorough review of the previous work activities identified in the work package is performed at the pre-job briefing for the planned work. Work activities should be discontinued if any confusion exists…

This occurrence demonstrated the use of data by engineering to evaluate equipment problems. As the data changed, highlighting a problem with one-half inch PVC ball valves, the facility redesigned the valve extension and valve handle to prevent…

This occurrence highlights the need for ensuring work is organized and planned in a manner that is practical and efficient. The primary lesson learned from this occurrence is that personnel must be cognizant of the impact of their actions on…

Cause and effect can sometimes be predicted by observing abnormal behavior even when the behavior is within specifications. Operators log equipment data and inform shift management when specifications are exceeded or when unusual equipment…

  1. Parallel-path design activities require an increased level of management oversight and control to mitigate the risks inherent in this process.
  2. Schedule pressure cannot be allowed to compromise the integrity of the design process…

In this case, failure to recognize a run of tubing still maintaining pressure could have been avoided if such information was provided in a safety briefing. Knowledge of any job is the utmost importance in promoting and maintaining a safe working…

This incident highlights the need to ensure that the performance of special procedures does not place facility equipment in a condition that could lead to entry into a LCO.

A step was added to the laboratory procedure in which all catalyst waste is thoroughly dampened with water and sealed in a plastic bag before being placed into a waste container.

Safe work procedures will be prepared and followed. Hydrogen will be vented out of the system to create an inert atmosphere before working on system tubing and joints. The importance of purging hydrogen piping and equipment is discussed in the…

Manuals showing the correct connecting and disconnecting procedures were established for each fueling dispenser. Separate manuals were needed since the shape of the grip differs from dispenser to dispenser.

Follow CGA G-5.5 vent end system designs.

Mechanical pressure gauges tend to be imprecise if only used in a narrow portion of the full scale. Digital transducers, although slightly more expensive, offer much more precision. The event happened because the set pressure was only 10% of full…

Corrective actions included replacing the breakaway with a new one, which restored normal operation of the dispenser.

Verify and periodically inspect the pull/separation force adjustment if the breakaway is so equipped.

Additional…

A gas detector was added in close proximity to the compressor shaft and a vibration switch is under consideration. Additional predictive measures are being considered to predict bearing failure. In addition, the manufacturer has been contacted…

Included inspection on monthly preventive maintenance plan and evaluated alternate materials for better cold-weather performance.

The fitting was an SAE straight thread and was likely loosened by torque applied to the fueling hose. After the incident, these fittings had additional means applied to restrict loosening, a cover installed to deflect any leakage, and means taken…

The possible outcomes from new maintenance scenarios can be predicted by using an accurate simulation. The proposed filter change-out maintenance was studied to identify conditions to which the catalyst might be exposed and a mock-up of the…

  1. Hydrogen safety training should be provided to local emergency responders.
  2. Liquid hydrogen installations should be inspected by facility personnel on a frequent basis, consistent with NFPA 55, to verify proper operation and…

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / CauseEquipment Design or SelectionComponent FailureOperational ErrorInstallation or MaintenanceInadequate Gas or Flame DetectionEmergency Shutdown ResponseOther or Unknown
Hydrogen Gas Metal Cylinder or Regulator 3/31/2012
4/30/1995
2/6/2013
4/26/201012/31/1969  3/17/1999
11/1/2001
12/23/2003
Piping/Valves4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/20091/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009
9/1/1992
10/31/1980
10/3/2008 
Tubing/Fittings/Hose 9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/19829/30/2004
10/7/2005
 10/7/2005 
Compressor 10/5/2009
6/10/2007
8/21/2008
1/15/2019
  10/5/20098/21/2008 
Liquid Hydrogen Tank or Delivery Truck4/27/198912/19/2004
1/19/2009
8/6/200412/31/1969 1/1/197412/17/2004
Pressure Relief Device7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969    
Instrument1/15/20193/17/1999
12/31/1969
2/6/2013
  11/13/73  
Hydrogen Generation Equipment7/27/1999  10/23/2001   
Vehicle or Lift Truck 7/21/2011    2/8/2011
12/9/2010
Fuel Dispenser 8/2/2004
5/1/2007
6/11/2007
9/19/2007
 2/24/2006
1/22/2009
   
Fuel Cell Stack      5/3/2004
12/9/2010
2/8/2011
Hydrogen Cooled Generator   12/31/1969
2/7/2009
   
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
 11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
  6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire
We are professional and reliable provider since we offer customers the most powerful and beautiful themes. Besides, we always catch the latest technology and adapt to follow world’s new trends to deliver the best themes to the market.

Contact info

We are the leaders in the building industries and factories. We're word wide. We never give up on the challenges.

Recent Posts