Severity
Incident
Was Hydrogen Released?
Yes
Was There Ignition?
Yes
Incident Date
Feb 03, 1996
Setting
Equipment
- Piping/Fittings/Valves
- Piping
Damage and Injuries
Probable Cause
Contributing Factors
When Incident Was Discovered
Lessons Learned
The SS 24-inch pipe that failed was replaced with 1-1/4 Cr 1/2 Mo alloy pipe that is corrosion-resistant to SCC. A revised HTS bypass piping layout was installed to prevent the hazardous conditions that lead to the failure. A detailed hazard review and evaluation of all of the materials of construction in the hydrogen plant process gas system led to preventively changing several other pieces of piping and equipment items in the SMR process to 1-1/4 Cr 1/2 Mo.
Post date
September, 2017
Key:
- = No Ignition
- = Explosion
- = Fire
- = No Ignition
- = Explosion
- = Fire