Skip to main content

Pipe Failure at Hydrogen Production Plant

Severity
Incident
Was Hydrogen Released?
Yes
Was There Ignition?
Yes
Incident Date
Incident Attributes
Equipment
Damage and Injuries
Probable Cause
Contributing Factors
When Incident Was Discovered
Describe the incident, including corrective steps taken and their result.

A pipe rupture occurred in a steam methane reformer (SMR) process that produces hydrogen and export steam. The rupture occurred in a 24-inch diameter stainless steel (SS) pipe used to allow the process gas flow to bypass the high-temperature shift converter (HTS) during start-up. When the pipe ruptured, process gas contained in process equipment located upstream and downstream of the break vented into the SMR plant yard area. The vented process gas was a mixture of hydrogen, carbon monoxide, carbon dioxide, steam, and methane at 550 psig and 650 deg F. The escaping high-pressure gas caused an energy release and subsequent fire. The fire was confined within the SMR plant, but equipment located near the pipe failure was damaged. The SMR plant distributed control system (DCS) worked properly to automatically shut down the process, thereby limiting the amount of process gas that escaped. Emergency response services were provided on the scene by the local county fire department within minutes of the incident and the fire was extinguished within 10 minutes. There were no injuries and no releases of any acutely hazardous materials covered by the Risk Management Prevention Plan (RMPP), EPA CERCLA, and SARA Title III regulations.

Metallurgical examination of the failed pipe segment revealed cracking on the pipe interior. The cracks were the result of stress corrosion cracking (SCC) of SS, caused by the presence of caustic (potassium hydroxide). The most likely source of the caustic was small amounts of potassium promoter normally present in the SMR catalyst. The section of the HTS bypass piping where the rupture occurred was normally cool and non-flowing. The piping layout allowed water and potassium hydroxide condensed from the process gas stream to collect in a low point. The SS material of construction of the bypass piping was susceptible to SCC from the concentrated caustic solution collecting in the bypass piping.

Lessons Learned

The SS 24-inch pipe that failed was replaced with 1-1/4 Cr 1/2 Mo alloy pipe that is corrosion-resistant to SCC. A revised HTS bypass piping layout was installed to prevent the hazardous conditions that lead to the failure. A detailed hazard review and evaluation of all of the materials of construction in the hydrogen plant process gas system led to preventively changing several other pieces of piping and equipment items in the SMR process to 1-1/4 Cr 1/2 Mo.

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / CauseEquipment Design or SelectionComponent FailureOperational ErrorInstallation or MaintenanceInadequate Gas or Flame DetectionEmergency Shutdown ResponseOther or Unknown
Hydrogen Gas Metal Cylinder or Regulator 3/31/2012
4/30/1995
2/6/2013
4/26/201012/31/1969  3/17/1999
11/1/2001
12/23/2003
Piping/Valves4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/20091/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009
9/1/1992
10/31/1980
10/3/2008 
Tubing/Fittings/Hose 9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/19829/30/2004
10/7/2005
 10/7/2005 
Compressor 10/5/2009
6/10/2007
8/21/2008
1/15/2019
  10/5/20098/21/2008 
Liquid Hydrogen Tank or Delivery Truck4/27/198912/19/2004
1/19/2009
8/6/200412/31/1969 1/1/197412/17/2004
Pressure Relief Device7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969    
Instrument1/15/20193/17/1999
12/31/1969
2/6/2013
  11/13/73  
Hydrogen Generation Equipment7/27/1999  10/23/2001   
Vehicle or Lift Truck 7/21/2011    2/8/2011
12/9/2010
Fuel Dispenser 8/2/2004
5/1/2007
6/11/2007
9/19/2007
 2/24/2006
1/22/2009
   
Fuel Cell Stack      5/3/2004
12/9/2010
2/8/2011
Hydrogen Cooled Generator   12/31/1969
2/7/2009
   
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
 11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
  6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire
We are professional and reliable provider since we offer customers the most powerful and beautiful themes. Besides, we always catch the latest technology and adapt to follow world’s new trends to deliver the best themes to the market.

Contact info

We are the leaders in the building industries and factories. We're word wide. We never give up on the challenges.

Recent Posts