Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.
These events show the importance of preventing combustible gas mixtures from accumulating in piping. In both of the above described events, hydrogen and oxygen gases apparently accumulated to a combustible level which then catastrophically failed…
An important lesson to be derived from this incident is the need to carefully engineer and test all repairs and modifications to high-pressure process equipment.
The SS 24-inch pipe that failed was replaced with 1-1/4 Cr 1/2 Mo alloy pipe that is corrosion-resistant to SCC. A revised HTS bypass piping layout was installed to prevent the hazardous conditions that lead to the failure. A detailed hazard…
Hydrogen distribution lines should be designed and carefully inspected to ensure process equipment in the area is correctly and safely installed. Equipment subject to vibration should not be placed in contact with hydrogen lines or with other…
Hydrogen distribution lines should be designed and carefully inspected to ensure process equipment in the area is correctly and safely installed. Equipment subject to vibration should not be placed in contact with hydrogen lines or with other…
An investigative communication notes that "mechanical integrity programs at refineries repeatedly emphasize inspection strategies rather then the use of inherently safer design to control the damage mechanisms that ultimately cause major process…
It is important to understand the requirements and standards associated with safe equipment design (especially electrical equipment containing an internal ignition source with flammable gas) in potentially explosive atmosphere environments.…
Based on the results of the company investigation and analysis of an amateur video, the company determined that the incident could have been caused by the failure of one of the following plant components:
· pipes leading to the reactor…
1. Management must ensure that operating decisions are not based primarily on cost and production. Performance goals and operating risks must be effectively communicated to all employees. Facility management must set safe, achievable operating…
1. Management must ensure that operating decisions are not based primarily on cost and production. Performance goals and operating risks must be effectively communicated to all employees. Facility management must set safe, achievable operating…
Management should ensure that a complete and thorough review of the previous work activities identified in the work package is performed at the pre-job briefing for the planned work. Work activities should be discontinued if any confusion exists…