Skip to main content

Equipment

CHECK OUT OUR MOST RELEVANT INCIDENT LISTINGS!

Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.

  • All tank trailers should have a safely accessible auxiliary shut off valve in case of spills.
  • Emergency personnel need to have access to all of the appropriate protective clothing, including shoes. Liquid hydrogen is stored at 20…

Standard procedure must be followed in all cases. Assumptions are made at great risk. Risk also increases with complacency.

Standard procedures must be followed at all times. The importance of doing so should be frequently reinforced through safety communications to all staff.

The use of inerting gas or other means of separation should be employed when conducting mechanical work where hydrogen gas could be present. More importantly, per CGA S1.3, the vessel should be equipped with a dual relief system that can isolate…

Extra caution should be taken working around elevated pressure or low-temperature fluids and storage. Values should be checked and then verified by a second party, if possible.

All valves and connectors should be clearly labeled to minimize chances for mis-connection. All technicians must be trained on proper procedures for both taking systems offline and bringing them back online.

Valves for compressed hydrogen…

First, it appears that the system may not have been vented properly. CGA G-5.5 should be used for determining safe locations based on the variables of the specific setup. Also, if the compressor was tied to a storage system, a backflow prevention…

Because of the near invisibility of a hydrogen flame in daylight and hydrogen's extremely low ignition coefficient, if a known leak is present (e.g., an audible hissing), ignition should always be presumed. The primary cause of this incident…

The tube was 403 stainless steel, which is subject to hydrogen embrittlement. It is requested that all gauges that have bourdon tubes be replaced with 303 stainless steel.

A web-based resource developed by Sandia National Laboratories to…

The charging characteristics of a battery vary with the condition of the battery and are proportional to the ampere-hour capacity of the battery. During charging, when a battery is close to being fully charged, hydrogen and oxygen both offgas in…

It is characteristic of silver/zinc batteries to outgas both hydrogen and oxygen for several hours after discharge. Also, in the future, the battery should be properly secured inside the container.

Refueling operations need to be conducted in a careful and attentive manner, and operators need to be aware of the potential consequences of their actions.

The site needs to implement a good Operational and Readiness Inspection procedure. System inspection deficiencies need to be identified, and (if possible) reviewed by a second party before future tests are conducted. This inspection could include…

Proper bolt identification can prevent similar occurrences in the future. This can be achieved by simply painting the critical bolt heads a certain color (or by purchasing bolts with painted bolt heads). An explanation form should then be clearly…

Extra caution should be taken when working around elevated pressure storage tanks. Pressure relief valve settings should be checked and then verified by a second party if possible. Proper procedures need to be followed at all times.

  • Facilities housing battery charging systems need to ensure the ventilation systems are operational, and delivering enough outdoor air to properly ventilate the enclosure.
  • Operators need to be aware of safe practices and proper…

Normally hydrogen fires are not extinguished until the supply of hydrogen has been shut off due to the danger of re-ignition and explosion. During a gas leak/fire, it is important to shut off the source of the hydrogen if it is safe to do so. If…

Lessons Learned The site initiated the establishment of a field patrol and strengthened their onsite monitoring of mechanical equipment during a plant-wide temperature rise.

  • Quantitative control of tightening torque on bolts…

Lessons Learned
Construction errors are difficult to detect once construction is complete. It is important to develop and use a systematic oversight process for minimizing construction errors during the construction process.

The uncontrolled release of hydrogen occurred as a result of the rupture of the No. 6 hydrogen storage tube’s burst disc. This disc failed in response to being overloaded by mechanical stresses developed as water expanded and formed ice while in…

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / CauseEquipment Design or SelectionComponent FailureOperational ErrorInstallation or MaintenanceInadequate Gas or Flame DetectionEmergency Shutdown ResponseOther or Unknown
Hydrogen Gas Metal Cylinder or Regulator 3/31/2012
4/30/1995
2/6/2013
4/26/201012/31/1969  3/17/1999
11/1/2001
12/23/2003
Piping/Valves4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/20091/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009
9/1/1992
10/31/1980
10/3/2008 
Tubing/Fittings/Hose 9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/19829/30/2004
10/7/2005
 10/7/2005 
Compressor 10/5/2009
6/10/2007
8/21/2008
1/15/2019
  10/5/20098/21/2008 
Liquid Hydrogen Tank or Delivery Truck4/27/198912/19/2004
1/19/2009
8/6/200412/31/1969 1/1/197412/17/2004
Pressure Relief Device7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969    
Instrument1/15/20193/17/1999
12/31/1969
2/6/2013
  11/13/73  
Hydrogen Generation Equipment7/27/1999  10/23/2001   
Vehicle or Lift Truck 7/21/2011    2/8/2011
12/9/2010
Fuel Dispenser 8/2/2004
5/1/2007
6/11/2007
9/19/2007
 2/24/2006
1/22/2009
   
Fuel Cell Stack      5/3/2004
12/9/2010
2/8/2011
Hydrogen Cooled Generator   12/31/1969
2/7/2009
   
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
 11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
  6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire
We are professional and reliable provider since we offer customers the most powerful and beautiful themes. Besides, we always catch the latest technology and adapt to follow world’s new trends to deliver the best themes to the market.

Contact info

We are the leaders in the building industries and factories. We're word wide. We never give up on the challenges.

Recent Posts