Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.
The hydrogen facility does not meet industrial guidelines for facilities of this type, from the standpoint of (1) the separation distance needed between a hydrogen pipe break and the building ventilation intake to prevent buildup of a flammable…
In any event, the lesson that should be derived from this incident is the fact that the explosion could have been avoided either by using an inert gas instead of air across the diaphragm, or by monitoring the hydrogen concentration in the upper…
As demonstrated by the fire discussed above, lack of adequate maintenance, system monitoring and oversight of maintenance of these facilities can contribute to the ignition of a fire that is difficult to extinguish and poses an extreme danger to…
Designs for high-tech systems/components evolve based on operating experience. The design changes should resolve identified deficiencies and are part of a continuous improvement process to increase reliability and productivity.
Whenever a new program or organization is created, management should ensure that program interfaces and new responsibilities are clearly defined. Effective program integration is necessary to ensure that all responsibilities and requirements are…
Recommendation 1 - Overhaul and replace the diaphragms on all cells showing low-purity results. Check on a routine basis the individual cell purity levels to monitor the deterioration of performance of individual cells. Certain…
No Lessons Learned, Specific Suggestions for Avoidance, or Mitigation Steps Taken.
Extra caution should be taken when working around elevated pressure storage tanks. Pressure relief valve settings should be checked and then verified by a second party if possible. Proper procedures need to be followed at all times.
Fail-safe position of control valves in supply lines must be set correctly to prevent damage to pressure vessels.
Recommendation
Set all valves for fail safe operation (open or closed) according to needs before installation…
The use of inerting gas or other means of separation should be employed when conducting mechanical work where hydrogen gas could be present. More importantly, per CGA S1.3, the vessel should be equipped with a dual relief system that can isolate…
Extra caution should be taken working around elevated pressure or low-temperature fluids and storage. Values should be checked and then verified by a second party, if possible.
Included inspection on monthly preventive maintenance plan and evaluated alternate materials for better cold-weather performance.
Recommendations: