CHECK OUT OUR MOST RELEVANT INCIDENT LISTINGS! 

Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.

The researcher's failure to pull the fire alarm was an oversight of required facility practice. The alarm should have been triggered in consideration of the potential for greater harm to personnel and facilities.

Hot, reacting ammonia…

Carbon steel Nelson curve methodology cannot be depended on to prevent HTHA equipment failures and cannot be reliably used to predict the occurrence of HTHA equipment damage. Revisions to recommended practices should be considered regarding the…

An important aspect of the reliability of a valve is the condition of the stem seal which tends to deteriorate with time and wear. Valves used in hydrogen service should be packed with the correct valve packing material and periodically checked…

The hydrogen supplier installed a fire-resistant material board adjacent to the high-pressure hydrogen storage banks to prevent any potential jet flames from affecting adjacent high-pressure cylinders for several minutes. The 0.25 mm sandwich…

Three root-causes were noted during the investigation: (1) the use of incompatible materials in the manufacturing of the PRD valve, (2) improper assembly resulting in over-torquing of the inner assembly, and (3) over-hardening of the inner…

Because the bottle was located outside at the time of the event, and the hydrogen did not find a source of ignition while venting through the relief valve, nothing serious happened. The failed regulator was replaced and operations continued.…

The following actions were proposed as a result of this incident: The company in charge of valve calibration and maintenance will be subject to approval of the plant service inspection team. Plant operating procedures will be improved. The…

The incident was the result of a combination of factors leading to exceptional temperature conditions that were not taken into account in the mechanical design of the reactor. Corrective actions that were implemented by the plant management…

In addition to the probable causes listed above, the lack of a standard operating procedure for hydrogen leak detection was one of the probable causes of this incident. Additional contributing factors included the following:
- Severe pipe…

Based on the results of the company investigation and analysis of an amateur video, the company determined that the incident could have been caused by the failure of one of the following plant components:
· pipes leading to the reactor…

Include the tanks in a regular inspection program. Evaluate their condition and replace if necessary.
Fill the tanks only half full with leach material.
Keep the material completely submerged in solution.
Install a fiberglass…

The ignition of the fireball could have been caused by any of the following mechanisms:

The inverse Joule-Thompson effect of hydrogen (i.e., heating upon expansion)
Some of the oil and light ends were above their auto-ignition…

The investigation team concluded that hydrogen gas was released through a failed 19-inch diameter gasket and ignited under the roof of the compressor shed where it was partially confined. Some gas escaped from the shed prior to the explosion, but…

The direct cause of the over-pressurization of the two drums was the repackaging of the phosphoric acid into metal UN1A1 drums and the resultant hydrogen gas generation within the sealed drums. At the time of this incident (1997), 49 CFR and…

The turbine components that caused the vibrations were a retrofit design which had been in service for about two years and were under warranty from the vendor. The root cause analysis of the event determined that the damage was caused by a defect…

Place signs on all liquid hydrogen tanks indicating that no water is to be put on the vent stack.
An additional secondary backup vent stack was added to liquid hydrogen tanks. This secondary stack is designed to be used only if needed in…

Mounting hardware incorporated polymeric braces not suitable for long-term exposure to sunlight and temperature extremes. With time, the polymeric materials had disintegrated, allowing the mounting brackets to become loose. In addition, the…

1. The trailer involved in the incident used a frangible burst disk based upon the proprietary metal compound designated as Inconel #600. Random sampling of similar pressure relief devices from the same trailer showed that all of them failed at…

Redundant safety systems prevented this event from becoming an incident. The 1%-hydrogen-concentration-level-triggered fan was backed up by a 2%-hydrogen-concentration alarm. The alarm is continuously monitored (24/7) by a remote Network…

The SS 24-inch pipe that failed was replaced with 1-1/4 Cr 1/2 Mo alloy pipe that is corrosion-resistant to SCC. A revised HTS bypass piping layout was installed to prevent the hazardous conditions that lead to the failure. A detailed hazard…

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / Cause Equipment Design or Selection Component Failure Operational Error Installation or Maintenance Inadequate Gas or Flame Detection Emergency Shutdown Response Other or Unknown
Hydrogen Gas Metal Cylinder or Regulator   3/31/2012
4/30/1995
2/6/2013
4/26/2010 12/31/1969     3/17/1999
11/1/2001
12/23/2003
Piping/Valves 4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/2009 1/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009

9/1/1992
10/31/1980

10/3/2008  
Tubing/Fittings/Hose   9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/1982 9/30/2004
10/7/2005
  10/7/2005  
Compressor   10/5/2009
6/10/2007
8/21/2008
1/15/2019
    10/5/2009 8/21/2008  
Liquid Hydrogen Tank or Delivery Truck 4/27/1989 12/19/2004
1/19/2009
8/6/2004 12/31/1969   1/1/1974 12/17/2004
Pressure Relief Device 7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969        
Instrument 1/15/2019 3/17/1999
12/31/1969
2/6/2013
    11/13/73    
Hydrogen Generation Equipment 7/27/1999     10/23/2001      
Vehicle or Lift Truck   7/21/2011         2/8/2011
12/9/2010
Fuel Dispenser   8/2/2004
5/1/2007
6/11/2007
9/19/2007
  2/24/2006
1/22/2009
     
Fuel Cell Stack            

5/3/2004
12/9/2010
2/8/2011

Hydrogen Cooled Generator       12/31/1969
2/7/2009
     
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
  11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
    6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire