CHECK OUT OUR MOST RELEVANT INCIDENT LISTINGS! 

Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.

Maintain an internal process for verifying component wetted material compatibility for intended use as part of the procurement process for hydrogen system equipment. 

Don’t rely solely on a manufacturer to provide appropriately rated…

The following actions were proposed as a result of this incident: The company in charge of valve calibration and maintenance will be subject to approval of the plant service inspection team. Plant operating procedures will be improved. The…

Carefully revise the risk assessment process to evaluate any confined areas where hydrogen is handled.
Separate the fire and gas detection alarm system from the process information to provide easy and clear identification.
Refresh…

The investigation team concluded that hydrogen gas was released through a failed 19-inch diameter gasket and ignited under the roof of the compressor shed where it was partially confined. Some gas escaped from the shed prior to the explosion, but…

The following corrective actions have been taken:

The non-return valve was dismantled, cleaned, and tested. Following positive testing, the system was restarted and pressurized without any further malfunctioning.
The hydrogen…

A gas detector was added in close proximity to the compressor shaft and a vibration switch is under consideration. Additional predictive measures are being considered to predict bearing failure. In addition, the manufacturer has been contacted…

The combination of the cold water temperature (reducing the fatigue strength of the bolt), and the abnormally high number of cyclical stresses imposed by the imbalance from the hydraulic system check valve failure resulted in the failure of the…

Failure of a diaphragm is not infrequent, but the seizure of the main nut threads is very rare. The manufacturer claimed this had never occurred before with this type of unit. The broken plunger is likely the result of poor instructions/…

This incident highlights the need to properly design safety interlocks. These safety interlocks need to be carefully incorporated into the initial building/plant designs and should consider all of the unexpected occurrences, such as the…

Maintain an internal process for verifying component wetted material compatibility for intended use as part of the procurement process for hydrogen system equipment. It is critical that component parts be appropriately rated for the materials,…

All valves and connectors should be clearly labeled to minimize chances for mis-connection. All technicians must be trained on proper procedures for both taking systems offline and bringing them back online.

Valves for compressed hydrogen…

First, it appears that the system may not have been vented properly. CGA G-5.5 should be used for determining safe locations based on the variables of the specific setup. Also, if the compressor was tied to a storage system, a backflow prevention…

Hydrogen distribution lines should be designed and carefully inspected to ensure process equipment in the area is correctly and safely installed. Equipment subject to vibration should not be placed in contact with hydrogen lines or with other…

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / Cause Equipment Design or Selection Component Failure Operational Error Installation or Maintenance Inadequate Gas or Flame Detection Emergency Shutdown Response Other or Unknown
Hydrogen Gas Metal Cylinder or Regulator   3/31/2012
4/30/1995
2/6/2013
4/26/2010 12/31/1969     3/17/1999
11/1/2001
12/23/2003
Piping/Valves 4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/2009 1/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009

9/1/1992
10/31/1980

10/3/2008  
Tubing/Fittings/Hose   9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/1982 9/30/2004
10/7/2005
  10/7/2005  
Compressor   10/5/2009
6/10/2007
8/21/2008
1/15/2019
    10/5/2009 8/21/2008  
Liquid Hydrogen Tank or Delivery Truck 4/27/1989 12/19/2004
1/19/2009
8/6/2004 12/31/1969   1/1/1974 12/17/2004
Pressure Relief Device 7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969        
Instrument 1/15/2019 3/17/1999
12/31/1969
2/6/2013
    11/13/73    
Hydrogen Generation Equipment 7/27/1999     10/23/2001      
Vehicle or Lift Truck   7/21/2011         2/8/2011
12/9/2010
Fuel Dispenser   8/2/2004
5/1/2007
6/11/2007
9/19/2007
  2/24/2006
1/22/2009
     
Fuel Cell Stack            

5/3/2004
12/9/2010
2/8/2011

Hydrogen Cooled Generator       12/31/1969
2/7/2009
     
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
  11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
    6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire