Deviation from Work Plan Results in Cutting Pipe Prior to Second Explosive Gas Test

First Name
Andy
Last Name
Piatt

A demolition technician noted an elevated combustible gas lower explosive limit (LEL) on a pipe that was being tested prior to cutting (No. 2 pipe). The No. 2 pipe was one of four pipes being tested. The other three pipes tested less than detectable for combustible hydrogen gas. Testing involves tapping the pipe and connecting the pipe to an Explosive Gas Detector via a tube. When an elevated LEL is identified, the pipe is allowed to vent and then retested prior to cutting. After tapping the No. 2 pipe, the work crew left the pipe open to vent and departed the area for the end of shift.

Combustible Gas Monitoring System in Furnace Room Found Inoperable

First Name
Andy
Last Name
Piatt

During a facility walk-through, it was noted that a combustible gas (hydrogen) monitoring system installed in a furnace room was inoperable (the system had been unplugged). This system is used to detect and warn facility employees of an explosive or flammable environment. An explosive or flammable environment can only occur if there is a leak in the system, which would not be expected to occur during normal operations. When the system was reactivated, no leaks were indicated.

The incident had the following three causes:

Saltwell Pump May Have Been Operated While the Standard Hydrogen Monitoring System was Not in Operational Mode

First Name
Andy
Last Name
Piatt

One morning a saltwell pump was placed in operation. Operation of this equipment requires that the Standard Hydrogen Monitoring System (SHMS) cabinet be in operation. Later that morning, during the morning surveillance rounds, the Standard Hydrogen Monitoring System (SHMS) cabinet was found not to be in the operational mode.

Failure of Stainless Steel Valves due to Hydrogen Embrittlement

First Name
Andy
Last Name
Piatt

Difficulties were experienced with two solenoid-operated globe valves in a charging system. When shut, the valves could not be reopened without securing all charging pumps. During a refueling outage, the two valves were disassembled and examined to determine the cause of the malfunction. It was found that disc guide assembly springs in both valves had undergone complete catastrophic failure. The springs, which initially had 25 coils, were found in sections of only 1-2 coils.

Pressure Reducing Clamp Removal Mishap

First Name
Andy
Last Name
Piatt

On a given day personnel were removing a blind hub that had been used to temporarily isolate a portion of a gaseous hydrogen system. As a result of a sudden release of 2,800 psig gaseous nitrogen, sand and debris kicked up from the concrete pad and caused minor injury to two technicians.

During the investigation, it was found that:

Liquid Hydrogen Refueling Operational Incident

First Name
Andy
Last Name
Piatt

Incident Synopsis
While disconnecting a liquid H2 fill line from a liquid H2 trailer, liquid H2 escaped, burning a second man who was holding the hose. The man was burned on his hands and on his stomach.

Cause
The liquid H2 shut off valve was partially open, but both men assumed it was closed. Prescribed clothing was being worn.

Hydrogen Boosting Compressor Fails

First Name
Andy
Last Name
Piatt

A single-stage diaphragm compressor failed during boosting of high-pressure hydrogen ground storage banks. The compressor sources hydrogen from a 44 MPa storage bank as suction and discharges it at a stop set point of 85 MPa. The compressor capacity is 0.71 m3/min (25 scfm).

Refinery Hydrocracker Pipe Ruptures and Releases Explosive Mixture with Hydrogen

First Name
Andy
Last Name
Piatt

A refinery hydrocracker effluent pipe section ruptured and released a mixture of gases, including hydrogen, which instantly ignited on contact with the air, causing an explosion and a fire. Excessive high temperature, likely in excess of 1400°F (760°C), initiated in one of the reactor beds spread to adjacent beds and raised the temperature and pressure of the effluent piping to the point where it failed. An operator who was checking a field temperature panel at the base of the reactor and trying to diagnose the high-temperature problem was killed.

Hydrogen Leak from Onboard Storage System of a Fuel Cell-Powered Lift Truck

First Name
Andy
Last Name
Piatt

A significant hydrogen leak occurred during refueling of the onboard hydrogen storage tank of a fuel cell-powered lift truck while it was completely depowered. The in-tank shutoff solenoid valve had recently been replaced, and this was the initial refueling event after the replacement. The fuel zone access panel was removed to allow constant visual leak checking with Snoop leak-detection fluid. The event occurred during the final pressure testing of the repaired system when an O-ring failed at approximately 4500 psi, releasing the entire contents of the hydrogen tank in about 10 minutes.

Pressure Relief Device Fails at Fueling Station

First Name
Andy
Last Name
Piatt

A pressure relief device (PRD) valve failed on a high-pressure storage tube at a hydrogen fueling station, causing the release of approximately 300 kilograms of hydrogen gas. The gas ignited at the exit of the vent pipe and burned for 2-1/2 hours until technicians were permitted by the local fire department to enter the station and stop the flow of gas. During this incident the fire department evacuated nearby businesses and an elementary school, closed adjacent streets, and ordered a high school to shelter in place.

Subscribe to Communication