Release of Hydrogen from a Gas Pipe in a Refinery
Around 13:45, a hydrogen leak on a pipe occurred in a refinery. Cold cutting of a purge was underway on the equipment as part of a work stoppage. The worker, who detected the leak, stopped the air saw and gave an alert. The installation was safe. The thousand employees presented was confined. A solid buffer was set up to isolate the section concerned by the leak.An error in identifying the location of the blowdown purge caused the event. A preparatory visit had been carried out a few months previously between the subcontractor in charge of the works and the subcontractor in charge of their preparation. A photograph was used, in addition to the isometric plans, to identify the installations. But the used photograph did not represent the good purge but its symmetrical compared to a manifold. The label materializing the location of the intervention was then placed on a hydrogen pipe in service. The pre-work checked and verified, focused on energy logging, failed to detect this error. There was no point on the spot, before starting work, between the intervener and the operator.Immediately after the incident, the operator reviewed its process of materializing the cutting sites. Tagging at the cut point by the facility manager become mandatory. The operator was reflecting on the solution to be retained for the entire refinery.The inspection of the classified installations, during a visit 6 days later, reminded the operator of its regulatory obligations in terms of joint inspection, operator / subcontractor, the pre-construction intervention zone and plans of prevention.
Event Date
October 12, 2016
Record Quality Indicator
Region / Country
Event Initiating System
Classification of the Physical Effects
Nature of the Consequences
Cause Comments
An error in identifying the location of the blowdown purge caused the event. A preparatory visit had been carried out a few months previously between the subcontractor in charge of the works and the subcontractor in charge of their preparation. A photograph was used, in addition to the isometric plans, to identify the installations. But the used photograph did not represent the good purge but its symmetrical compared to a manifold. The label materializing the location of the intervention was then placed on a hydrogen pipe in service. The pre-work checked and verified, focused on energy logging, failed to detect this error. There was no point on the spot, before starting work, between the intervener and the operator.
Facility Information
Application Type
Specific Application Supply Chain Stage
Components Involved
a pipe in a refinery
Storage/Process Medium
Location Type
Location description
Industrial Area
Pre-event Summary
An error in identifying the location of the blowdown purge caused the event. A preparatory visit had been carried out a few months previously between the subcontractor in charge of the works and the subcontractor in charge of their preparation. A photograph was used, in addition to the isometric plans, to identify the installations. But the used photograph did not represent the good purge but its symmetrical compared to a manifold. The label materializing the location of the intervention was then placed on a hydrogen pipe in service. The pre-work checked and verified, focused on energy logging, failed to detect this error. There was no point on the spot, before starting work, between the intervener and the operator.
Lessons Learned
Lessons Learned
Unknown
Event Nature
Emergency Action
The worker, who detected the leak, stopped the air saw and gave an alert. The installation was safe. The thousand employees presented was confined. A solid buffer was set up to isolate the section concerned by the leak.
Detonation
No
Deflagration
No
High Pressure Explosion
No
High Voltage Explosion
No
Source Category
References
References

ARIA data base
event no. 49064

We are professional and reliable provider since we offer customers the most powerful and beautiful themes. Besides, we always catch the latest technology and adapt to follow world’s new trends to deliver the best themes to the market.

Contact info

We are the leaders in the building industries and factories. We're word wide. We never give up on the challenges.

Recent Posts