Gaseous hydrogen can be stored forever as long as the system integrity is maintained. However, liquid hydrogen is “use it or lose it” and will boil from system heat leak and build pressure unless it is used or vented. This is not usually an issue for continuous use or low-pressure applications which can use hydrogen gas pressure directly from the tank.
For intermittent or high…
The HSP recommends against the use of glycols for pressure tests due to the difficulty of adequately removing all glycol that might be left in a system after a hydrotest. The HSP recommends a pneumatic test at 110% of the system maximum allowable working pressure (MAWP), which is acceptable by code. Due to an increased danger with pneumatics vs hydrotesting, establish a pressure test zone for…
The Panel recommends performing a pressure test at 110% of design pressure. This requirement should be applied to all systems regardless of construction type since the intent is to ensure pressure integrity and proper installation. All fitting types have modes of failure during installation. For example, there are numerous examples where compression fittings have had ferrules installed…
A "drop and swap" delivery system using tube trailers is a common and accepted method of supply for both industrial and fueling station applications. While NFPA 2 - 2023, paragraph 10.6.3.5 states, "The use of hose in a hydrogen dispensing system shall be limited to vehicle fueling hose," this is intended for the dispenser itself, not the entire fueling station. This does not limit the use of…
Many methods are used to mitigate the risk of a tube trailer hose loss of containment incident. Examples that otherwise exceed code requirements are provided below. These have been deployed in various combinations depending on the risk analysis for a particular system:
The code used for repair and alterations of an existing system depends on the code used for construction as well as on the requirements imposed by the jurisdiction. Note that getting a permit from the jurisdiction may be necessary for an extensive alteration.
Code of Construction | Generally Accepted Code for Repair and Alterations… Category: Piping Keywords: Piping, Codes
The requirements of the code used for the original construction apply. The piping may meet the requirements of more than one code. In which case, the code used for changing the rating may be different than the original code of construction. In any case, the re-rated system should meet all of the requirements of the selected code. Note that if the original proof test of the system was… Category: Piping Keywords: Codes, Piping, Requirements
At least three of the ASME B31 piping codes are logical choices:
Considerations for code selection include:
Category: Piping Keywords: Piping, Codes, Requirements
Hydrogen affects the mechanical properties of most materials. For example, hydrogen reduces the Category: Piping Keywords: Pipeline, Material Compatibility, ASME Standards, Pipeline Safety