CHECK OUT OUR MOST RELEVANT INCIDENT LISTINGS!
Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.
Redundant safety systems prevented this event from becoming an incident. The 1%-hydrogen-concentration-level-triggered fan was backed up by a 2%-hydrogen-concentration alarm. The alarm is continuously monitored (24/7) by a remote Network…
The following corrective actions have been taken:
The non-return valve was dismantled, cleaned, and tested. Following positive testing, the system was restarted and pressurized without any further malfunctioning.
The hydrogen…
Utilize a Six Sigma Black Belt to statistically evaluate LFL monitor reliability and determine the failure rate based on the existing technology.
Revise the tank uncertainty calculation and surveillance to include a wider "Required…
Frequently inspect and maintain all elements of hydrogen-related systems.
Cause and effect can sometimes be predicted by observing abnormal behavior even when the behavior is within specifications. Operators log equipment data and inform shift management when specifications are exceeded or when unusual equipment…
Parallel-path design activities require an increased level of management oversight and control to mitigate the risks inherent in this process.
Schedule pressure cannot be allowed to compromise the integrity of the design process.
…
This incident highlights the need to ensure that the performance of special procedures does not place facility equipment in a condition that could lead to entry into a LCO.
This incident occurred due to moisture in the sample line monitoring system. Removing moisture from the sample line increases the reliability of the equipment. Further evaluations are being considered for improving system reliability.
All safety devices worked as designed thereby protecting the environment and laboratory personnel. Researchers involved in the experiment acted properly and with the parameters set forth in operational procedures.
Follow up: Stops have…
Key:
- = No Ignition
- = Explosion
- = Fire
Equipment / Cause | Equipment Design or Selection | Component Failure | Operational Error | Installation or Maintenance | Inadequate Gas or Flame Detection | Emergency Shutdown Response | Other or Unknown |
---|---|---|---|---|---|---|---|
Hydrogen Gas Metal Cylinder or Regulator | 3/31/2012 4/30/1995 2/6/2013 |
4/26/2010 | 12/31/1969 | 3/17/1999 11/1/2001 12/23/2003 |
|||
Piping/Valves | 4/4/2002 2/2/2008 5/11/1999 |
4/20/1987 11/4/1997 12/31/1969 8/19/1986 7/27/1991 12/19/2004 2/6/2008 10/3/2008 4/5/2006 5/1/2007 9/19/2007 10/31/1980 |
2/7/2009 | 1/24/1999 2/24/2006 6/8/1998 12/31/1969 2/7/2009 |
10/3/2008 | ||
Tubing/Fittings/Hose | 9/23/1999 8/2/2004 8/6/2008 9/19/2007 |
1/1/1982 | 9/30/2004 10/7/2005 |
10/7/2005 | |||
Compressor | 10/5/2009 6/10/2007 8/21/2008 1/15/2019 |
10/5/2009 | 8/21/2008 | ||||
Liquid Hydrogen Tank or Delivery Truck | 4/27/1989 | 12/19/2004 1/19/2009 |
8/6/2004 | 12/31/1969 | 1/1/1974 | 12/17/2004 | |
Pressure Relief Device | 7/25/2013 5/4/2012 |
1/15/2002 1/08/2007 |
12/31/1969 | ||||
Instrument | 1/15/2019 | 3/17/1999 12/31/1969 2/6/2013 |
11/13/73 | ||||
Hydrogen Generation Equipment | 7/27/1999 | 10/23/2001 | |||||
Vehicle or Lift Truck | 7/21/2011 | 2/8/2011 12/9/2010 |
|||||
Fuel Dispenser | 8/2/2004 5/1/2007 6/11/2007 9/19/2007 |
2/24/2006 1/22/2009 |
|||||
Fuel Cell Stack | |||||||
Hydrogen Cooled Generator | 12/31/1969 2/7/2009 |
||||||
Other (floor drain, lab anaerobic chamber, heated glassware, test chamber, gaseous hydrogen composite cylinder, delivery truck) |
11/14/1994 7/21/2011 |
7/27/1999 6/28/2010 8/21/2008 |
12/31/1969 3/22/2018 |
6/10/2019 |
- = No Ignition
- = Explosion
- = Fire