CHECK OUT OUR MOST RELEVANT INCIDENT LISTINGS! 

Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.

Because the bottle was located outside at the time of the event, and the hydrogen did not find a source of ignition while venting through the relief valve, nothing serious happened. The failed regulator was replaced and operations continued.…

1.  Combustible gas detectors calibrated for hydrogen can falsely report hydrogen alarms due the presence of other gases the detector may pick up, such as carbon monoxide from engine exhaust or other sources. Since this event occurred, two…

The following corrective actions have been taken:

The non-return valve was dismantled, cleaned, and tested. Following positive testing, the system was restarted and pressurized without any further malfunctioning.
The hydrogen…

Safe work procedures will be prepared and followed. Hydrogen will be vented out of the system to create an inert atmosphere before working on system tubing and joints. The importance of purging hydrogen piping and equipment is discussed in the…

For the use of mechanical fittings in hydrogen service, administrative controls should be in place, as in this case, to ensure that leak testing is conducted on a regular basis. It should never be assumed that every fitting is tight. Additional…

The lessons of this event fall into five categories: (1) proper in-plant communications during events, (2) proper valve application for use with hydrogen, (3) excess flow check valve set point, (4) heating and ventilation and air conditioning (…

Installation

Fittings need to be visually inspected to insure ferules are in place and correctly positioned prior to swageing.
Research staff are responsible for communicating system specifications [gas type, Maximum Allowable…

Management should ensure that a complete and thorough review of the previous work activities identified in the work package is performed at the pre-job briefing for the planned work. Work activities should be discontinued if any confusion exists…

Hydrogen distribution lines should be designed and carefully inspected to ensure process equipment in the area is correctly and safely installed. Equipment subject to vibration should not be placed in contact with hydrogen lines or with other…

When performing maintenance evolutions, proper work control processes must be in place to insure that process systems are adequately prepared, remain in a safe energy state during the maintenance evolution, and are properly restored afterwards.…

In this case, failure to recognize a run of tubing still maintaining pressure could have been avoided if such information was provided in a safety briefing. Knowledge of any job is the utmost importance in promoting and maintaining a safe working…

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / Cause Equipment Design or Selection Component Failure Operational Error Installation or Maintenance Inadequate Gas or Flame Detection Emergency Shutdown Response Other or Unknown
Hydrogen Gas Metal Cylinder or Regulator   3/31/2012
4/30/1995
2/6/2013
4/26/2010 12/31/1969     3/17/1999
11/1/2001
12/23/2003
Piping/Valves 4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/2009 1/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009

9/1/1992
10/31/1980

10/3/2008  
Tubing/Fittings/Hose   9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/1982 9/30/2004
10/7/2005
  10/7/2005  
Compressor   10/5/2009
6/10/2007
8/21/2008
1/15/2019
    10/5/2009 8/21/2008  
Liquid Hydrogen Tank or Delivery Truck 4/27/1989 12/19/2004
1/19/2009
8/6/2004 12/31/1969   1/1/1974 12/17/2004
Pressure Relief Device 7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969        
Instrument 1/15/2019 3/17/1999
12/31/1969
2/6/2013
    11/13/73    
Hydrogen Generation Equipment 7/27/1999     10/23/2001      
Vehicle or Lift Truck   7/21/2011         2/8/2011
12/9/2010
Fuel Dispenser   8/2/2004
5/1/2007
6/11/2007
9/19/2007
  2/24/2006
1/22/2009
     
Fuel Cell Stack            

5/3/2004
12/9/2010
2/8/2011

Hydrogen Cooled Generator       12/31/1969
2/7/2009
     
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
  11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
    6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire