Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.
This incident highlights the need to properly design safety interlocks. These safety interlocks need to be carefully incorporated into the initial building/plant designs and should consider all of the unexpected occurrences, such as the…
All valves and connectors should be clearly labeled to minimize chances for mis-connection. All technicians must be trained on proper procedures for both taking systems offline and bringing them back online.
Valves for compressed hydrogen…
First, it appears that the system may not have been vented properly. CGA G-5.5 should be used for determining safe locations based on the variables of the specific setup. Also, if the compressor was tied to a storage system, a backflow prevention…
Failure of a diaphragm is not infrequent, but the seizure of the main nut threads is very rare. The manufacturer claimed this had never occurred before with this type of unit. The broken plunger is likely the result of poor instructions/…
The investigation team concluded that hydrogen gas was released through a failed 19-inch diameter gasket and ignited under the roof of the compressor shed where it was partially confined. Some gas escaped from the shed prior to the explosion, but…
- Carefully revise the risk assessment process to evaluate any confined areas where hydrogen is handled.
- Separate the fire and gas detection alarm system from the process information to provide easy and clear identification.…
The following actions were proposed as a result of this incident:
- The company in charge of valve calibration and maintenance will be subject to approval of the plant service inspection team.
- Plant operating…
Key:
- = No Ignition
- = Explosion
- = Fire
Equipment / Cause | Equipment Design or Selection | Component Failure | Operational Error | Installation or Maintenance | Inadequate Gas or Flame Detection | Emergency Shutdown Response | Other or Unknown |
---|---|---|---|---|---|---|---|
Hydrogen Gas Metal Cylinder or Regulator | 3/31/2012 4/30/1995 2/6/2013 |
4/26/2010 | 12/31/1969 | 3/17/1999 11/1/2001 12/23/2003 |
|||
Piping/Valves | 4/4/2002 2/2/2008 5/11/1999 |
4/20/1987 11/4/1997 12/31/1969 8/19/1986 7/27/1991 12/19/2004 2/6/2008 10/3/2008 4/5/2006 5/1/2007 9/19/2007 10/31/1980 |
2/7/2009 | 1/24/1999 2/24/2006 6/8/1998 12/31/1969 2/7/2009 |
10/3/2008 | ||
Tubing/Fittings/Hose | 9/23/1999 8/2/2004 8/6/2008 9/19/2007 |
1/1/1982 | 9/30/2004 10/7/2005 |
10/7/2005 | |||
Compressor | 10/5/2009 6/10/2007 8/21/2008 1/15/2019 |
10/5/2009 | 8/21/2008 | ||||
Liquid Hydrogen Tank or Delivery Truck | 4/27/1989 | 12/19/2004 1/19/2009 |
8/6/2004 | 12/31/1969 | 1/1/1974 | 12/17/2004 | |
Pressure Relief Device | 7/25/2013 5/4/2012 |
1/15/2002 1/08/2007 |
12/31/1969 | ||||
Instrument | 1/15/2019 | 3/17/1999 12/31/1969 2/6/2013 |
11/13/73 | ||||
Hydrogen Generation Equipment | 7/27/1999 | 10/23/2001 | |||||
Vehicle or Lift Truck | 7/21/2011 | 2/8/2011 12/9/2010 |
|||||
Fuel Dispenser | 8/2/2004 5/1/2007 6/11/2007 9/19/2007 |
2/24/2006 1/22/2009 |
|||||
Fuel Cell Stack | |||||||
Hydrogen Cooled Generator | 12/31/1969 2/7/2009 |
||||||
Other (floor drain, lab anaerobic chamber, heated glassware, test chamber, gaseous hydrogen composite cylinder, delivery truck) |
11/14/1994 7/21/2011 |
7/27/1999 6/28/2010 8/21/2008 |
12/31/1969 3/22/2018 |
6/10/2019 |
- = No Ignition
- = Explosion
- = Fire