A facility representative observed pipe-fitters enter a containment tent around a riser with a tool bag that contained a mixture of steel and copper/beryllium tools. The top flange was loosened using a copper/beryllium socket and a steel torque wrench. When questioned, the pipe-fitters correctly stated that this was allowable for initial loosening and tightening of these bolts. A copper/beryllium ratchet was used to accomplish the bolt removal. The bonded riser was shifted to allow access for the IH technician. The standard hydrogen monitoring system (SHMS) cabinet and local sample showed no hydrogen/flammable gas was present.

While the continuous vapor sample was being taken, the pipe-fitters proceeded to put together the copper/beryllium ratchet and socket with a 10" view more

An operator went to purge a process tank per standard operating procedure. The operator reviewed the previous shift's purge time and determined the next required purge time. The operator found that the tank had been purged earlier than expected on the previous shift. Because the earlier purge time was not recognized, the 12-hour purge frequency was exceeded.

Background: On the previous day, during the night shift, an operator performed 12-hour hydrogen purges per the requirements of the standard operating procedure. Each of the hydrogen purges was completed within the required time limits. The operator correctly recorded the time and date that the next hydrogen purges would be required. The following morning, shift turnover was conducted. The direct and root cause of this view more