This incident illustrates how difficult it is to completely purge hydrogen out of a large, complex piece of equipment. Uniform mixing and dilution is unlikely in all the partially enclosed spaces, crevices, etc. If a hazardous operation such as…
Personnel should be properly supervised, and supervisors should be aware of the activities of their personnel. Personnel must be motivated to adhere to established policies and procedures. All personnel associated with potentially hazardous work…
Because of the near invisibility of a hydrogen flame in daylight and hydrogen's extremely low ignition coefficient, if a known leak is present (e.g., an audible hissing), ignition should always be presumed. The primary cause of this incident…
The tube was 403 stainless steel, which is subject to hydrogen embrittlement. It is requested that all gauges that have bourdon tubes be replaced with 303 stainless steel.
A web-based resource developed by Sandia National Laboratories to…
- Train personnel on delivery procedures and emphasize the safety aspects of hydrogen connections and disconnections, and verification of clearance for trailer movement prior to departure.
- Provide site-specific delivery procedures…
In addition to the probable causes listed above, the lack of a standard operating procedure for hydrogen leak detection was one of the probable causes of this incident. Additional contributing factors included the following:
- Severe pipe…
The following actions were proposed as a result of this incident:
- The company in charge of valve calibration and maintenance will be subject to approval of the plant service inspection team.
- Plant operating…
Key:
- = No Ignition
- = Explosion
- = Fire
Equipment / Cause | Equipment Design or Selection | Component Failure | Operational Error | Installation or Maintenance | Inadequate Gas or Flame Detection | Emergency Shutdown Response | Other or Unknown |
---|---|---|---|---|---|---|---|
Hydrogen Gas Metal Cylinder or Regulator | 3/31/2012 4/30/1995 2/6/2013 |
4/26/2010 | 12/31/1969 | 3/17/1999 11/1/2001 12/23/2003 |
|||
Piping/Valves | 4/4/2002 2/2/2008 5/11/1999 |
4/20/1987 11/4/1997 12/31/1969 8/19/1986 7/27/1991 12/19/2004 2/6/2008 10/3/2008 4/5/2006 5/1/2007 9/19/2007 10/31/1980 |
2/7/2009 | 1/24/1999 2/24/2006 6/8/1998 12/31/1969 2/7/2009 |
10/3/2008 | ||
Tubing/Fittings/Hose | 9/23/1999 8/2/2004 8/6/2008 9/19/2007 |
1/1/1982 | 9/30/2004 10/7/2005 |
10/7/2005 | |||
Compressor | 10/5/2009 6/10/2007 8/21/2008 1/15/2019 |
10/5/2009 | 8/21/2008 | ||||
Liquid Hydrogen Tank or Delivery Truck | 4/27/1989 | 12/19/2004 1/19/2009 |
8/6/2004 | 12/31/1969 | 1/1/1974 | 12/17/2004 | |
Pressure Relief Device | 7/25/2013 5/4/2012 |
1/15/2002 1/08/2007 |
12/31/1969 | ||||
Instrument | 1/15/2019 | 3/17/1999 12/31/1969 2/6/2013 |
11/13/73 | ||||
Hydrogen Generation Equipment | 7/27/1999 | 10/23/2001 | |||||
Vehicle or Lift Truck | 7/21/2011 | 2/8/2011 12/9/2010 |
|||||
Fuel Dispenser | 8/2/2004 5/1/2007 6/11/2007 9/19/2007 |
2/24/2006 1/22/2009 |
|||||
Fuel Cell Stack | |||||||
Hydrogen Cooled Generator | 12/31/1969 2/7/2009 |
||||||
Other (floor drain, lab anaerobic chamber, heated glassware, test chamber, gaseous hydrogen composite cylinder, delivery truck) |
11/14/1994 7/21/2011 |
7/27/1999 6/28/2010 8/21/2008 |
12/31/1969 3/22/2018 |
6/10/2019 |
- = No Ignition
- = Explosion
- = Fire