CHECK OUT OUR MOST RELEVANT INCIDENT LISTINGS! 

Disclaimer: The Lessons Learned Database includes the incidents that were voluntarily submitted. The database is not a comprehensive source for all incidents that have occurred.

Hydrogen safety training should be provided to local emergency responders.
Liquid hydrogen installations should be inspected by facility personnel on a frequent basis, consistent with NFPA 55, to verify proper operation and inspect for…

The possible outcomes from new maintenance scenarios can be predicted by using an accurate simulation. The proposed filter change-out maintenance was studied to identify conditions to which the catalyst might be exposed and a mock-up of the…

Metallurgical examination of the two failed disks by light optical microscopy (LOM), scanning electron microscopy (SEM), and energy-dispersive x-ray spectroscopic analysis (EDS) found them to be fabricated from pure nickel with evidence of…

The following corrective actions have been taken:

The non-return valve was dismantled, cleaned, and tested. Following positive testing, the system was restarted and pressurized without any further malfunctioning.
The hydrogen…

Specific response drills/exercises need to be conducted yearly. In this case, all safety systems worked as they should and outside emergency responders were not needed.
Performing other tasks while filling hydrogen tube trailers, such as…

1. Evaluate any change in normal procedures or conditions for storage of aluminum hydride products. In this case, the aluminum hydride material was typically stored at -35°C in the glove box freezer. However, due to a change in glove boxes, this…

The fitting was an SAE straight thread and was likely loosened by torque applied to the fueling hose. After the incident, these fittings had additional means applied to restrict loosening, a cover installed to deflect any leakage, and means taken…

Included inspection on monthly preventive maintenance plan and evaluated alternate materials for better cold-weather performance.

A gas detector was added in close proximity to the compressor shaft and a vibration switch is under consideration. Additional predictive measures are being considered to predict bearing failure. In addition, the manufacturer has been contacted…

Corrective actions included replacing the breakaway with a new one, which restored normal operation of the dispenser.Verify and periodically inspect the pull/separation force adjustment if the breakaway is so equipped.Additional information on…

Mechanical pressure gauges tend to be imprecise if only used in a narrow portion of the full scale. Digital transducers, although slightly more expensive, offer much more precision. The event happened because the set pressure was only 10% of full…

Consider periodic testing of breakaway device.
Consider determining shear force limit of vehicle receptacle adapter fittings.

Several recommendations were outlined by the investigating committee to govern future operations of the hydrogen compressor in the synthetic liquid fuels laboratory:

Install a cutoff that will shut down the compressor when the suction…

1. Ensure that equipment and materials exposed to hydrogen are compatible with a hydrogen environment (even hydrogen-service-rated equipment).

2. Equipment designs in a hydrogen environment that use the fracture toughness for 17-4…

The packing in the flow control valve should be replaced periodically. A planned investigation will determine the optimum time period for packing replacement.

Manuals showing the correct connecting and disconnecting procedures were established for each fueling dispenser. Separate manuals were needed since the shape of the grip differs from dispenser to dispenser.

Inadequate Safeguards - The system was designed with low-point drains to facilitate water removal, however, these were found to be inadequate in both location and size. The fact that the mixed feed pre-heat coil was not self-draining was unknown…

Train personnel on delivery procedures and emphasize the safety aspects of hydrogen connections and disconnections, and verification of clearance for trailer movement prior to departure.
Provide site-specific delivery procedures and…

Defects in equipment, such as welds, may not be evident during initial proof testing and operation.
When an equipment defect is found, check equipment for possible similar defects in other areas of the equipment.

The following recommended actions were identified:

Reemphasize the current lab management policies and practices on how process changes are evaluated for direct/indirect impacts on the process.
Reinforce with lab workers the…

Key:

  • = No Ignition
  • = Explosion
  • = Fire
Hydrogen Incident Summaries by Equipment and Primary Cause/Issue
Equipment / Cause Equipment Design or Selection Component Failure Operational Error Installation or Maintenance Inadequate Gas or Flame Detection Emergency Shutdown Response Other or Unknown
Hydrogen Gas Metal Cylinder or Regulator   3/31/2012
4/30/1995
2/6/2013
4/26/2010 12/31/1969     3/17/1999
11/1/2001
12/23/2003
Piping/Valves 4/4/2002
2/2/2008
5/11/1999
4/20/1987
11/4/1997
12/31/1969
8/19/1986
7/27/1991
12/19/2004
2/6/2008
10/3/2008
4/5/2006
5/1/2007
9/19/2007
10/31/1980
2/7/2009 1/24/1999
2/24/2006
6/8/1998
12/31/1969
2/7/2009

9/1/1992
10/31/1980

10/3/2008  
Tubing/Fittings/Hose   9/23/1999
8/2/2004
8/6/2008
9/19/2007
1/1/1982 9/30/2004
10/7/2005
  10/7/2005  
Compressor   10/5/2009
6/10/2007
8/21/2008
1/15/2019
    10/5/2009 8/21/2008  
Liquid Hydrogen Tank or Delivery Truck 4/27/1989 12/19/2004
1/19/2009
8/6/2004 12/31/1969   1/1/1974 12/17/2004
Pressure Relief Device 7/25/2013
5/4/2012
1/15/2002
1/08/2007
12/31/1969        
Instrument 1/15/2019 3/17/1999
12/31/1969
2/6/2013
    11/13/73    
Hydrogen Generation Equipment 7/27/1999     10/23/2001      
Vehicle or Lift Truck   7/21/2011         2/8/2011
12/9/2010
Fuel Dispenser   8/2/2004
5/1/2007
6/11/2007
9/19/2007
  2/24/2006
1/22/2009
     
Fuel Cell Stack            

5/3/2004
12/9/2010
2/8/2011

Hydrogen Cooled Generator       12/31/1969
2/7/2009
     
Other (floor drain, lab
anaerobic chamber,
heated glassware,
test chamber,
gaseous hydrogen
composite cylinder,
delivery truck)
  11/14/1994
7/21/2011
7/27/1999
6/28/2010
8/21/2008
12/31/1969
3/22/2018
    6/10/2019
  • = No Ignition
  • = Explosion
  • = Fire